South Korea completes Uldolmok tidal plant
Posted by Big Gav in ocean energy, south korea, tidal power, uldolmok
International Water power magazine reports that the first phase of a South Korean tidal power plant has been completed - South Korea completes Uldolmok tidal plant.
South Korea has completed construction of the first tidal power plant, at Uldolmok, and the installed capacity is to be incrementally increased over the next four years.
Starting with 1MW of capacity the plant will be increased in size to 90MW by 2013. Construction of the Uldolmok plant began in 2005.
While the plant, located in the Jindo region, is a milestone for the country it is much smaller than the tidal scheme at Sihwa, which is currently being built. The Sihwa plant will have an installed capacity of 254MW. ...
In late 2006, Voith Hydro (then Voith Siemens Hydro) also became active in tidal developments in South Korea with plans for a joint venture agreed with Korea Hydro & Nuclear Power Co, Posco, Renetex and the provicial government of Jeonnan. The JV was signed two years ago and has been looking at construction of a 600MW plant in Wando province.
Separately, Korean Midland Power Co and UK firm Lunar Energy are examining construction of a 300MW tidal scheme at Wando Hoenggan Water Way. The technology would be supplied by Rotech Engineering and Hyundai.